Delivery record

Where complexity is
the baseline.

17 projects as PM or Senior PM. Started on the tools - steel fabricator, handyman, multi-skilled operative, site manager - before moving into PM in 2013. Active in the industry since 2005. Specialising in heritage buildings, secure government estates, and live-occupied environments.

8

Government & Secure

6

Live-Occupied

5

Commercial Office

4

Heritage & Listed

GALLERY FIT-OUTLIVE MUSEUMHERITAGEOCCUPIED BUILDINGCAT BDESIGN & BUILD

Science Museum

Wonderlab Interactive Gallery

Asbestos removal, strip out and full refurbishment to create the Wonderlab interactive gallery within an operational museum. Coordinated specialist contractors to install interactive exhibits sourced from the USA, Europe and the UK. Bespoke joinery package including a suspended auditorium.

SCOPE

Interactive Gallery, 44 Specialists

COMPLETED

January to October 2016

ROLE

Project Manager

CLIENT

Science Museum Group (via Paragon)

Science Museum Wonderlab - gallery
Science Museum Wonderlab - interactive exhibits
Science Museum Wonderlab - auditorium
Science Museum Wonderlab - installation
Science Museum Wonderlab - detail
HERITAGEGRADE II LISTEDREFURBISHMENTCAT BDESIGN & BUILD

Lincoln's Inn

2 New Square, Lincoln's Inn

Strip out, refurbishment and Cat B fit-out of 17th-century Grade II listed barristers' chambers. Scaffold to roofline, roof works, two new lifts installed within a listed shell, new stone staircase, external drainage and incoming mains services. Sensitive heritage restoration delivered within a historic listed building.

SCOPE

Heritage Restoration, Cat B

COMPLETED

2012-2013

ROLE

Site Manager

CLIENT

Lincoln's Inn (via Paragon)

Lincoln's Inn - 2 New Square
Lincoln's Inn - heritage restoration
Lincoln's Inn - fit-out detail
CAT ACAT BDESIGN & BUILD

The Shard

Levels 14 and 22

Reinstatement of the 14th floor from Cat B back to Cat A, plus a new marketing suite on the 22nd floor. Complex logistics and a tight programme in one of London's most recognisable towers.

SCOPE

Cat A + New Marketing Suite

COMPLETED

April to September 2013

ROLE

Project Manager

CLIENT

Sellar Group (via Paragon)

The Shard - Cat A fit-out
The Shard - marketing suite
The Shard - level detail
HERITAGEGOVERNMENTOCCUPIED BUILDINGSECURECAT BDESIGN & BUILD

Royal Courts of Justice

Thomas More Building

Strip out, asbestos removal and Cat B fit-out of 11 floors within the Thomas More Building. Courtrooms, judges' rooms and restricted-access areas. Specialist subcontractor coordination throughout a live judicial building.

SCOPE

Cat B Fit-Out, 11 Floors

COMPLETED

September 2013 to May 2014

ROLE

Project Manager

CLIENT

MOJ / HMCTS (via Paragon)

Royal Courts of Justice - Thomas More Building
Royal Courts of Justice - interior detail
CAT ACAT BCOMMERCIALOCCUPIED BUILDINGDESIGN & BUILD

110 High Holborn

Floors 5 to 8

Strip out to shell and core across four floors with full Cat A and Cat B installation: chilled beams, LED lighting, new ceilings and raised floor. Reception works included. The quality presentation prepared for this project was subsequently adopted as standard across other Paragon projects.

SCOPE

Cat A & Cat B, Floors 5-8 and Reception

COMPLETED

2014-2015

ROLE

Project Manager

CLIENT

Investment Group (via Paragon)

110 High Holborn - Cat A fit-out
110 High Holborn - floor installation
110 High Holborn - interior
GOVERNMENTSECURECAT BOCCUPIED BUILDINGDESIGN & BUILD

MOJ, 102 Petty France

Phases 1, 2 and 3

Phased Cat B fit-out and refurbishment across three government buildings. Scope included reception refurbishment, secure walls and portals, meeting rooms and office reconfiguration across eleven floors. Live and secure environment maintained throughout with full business continuity across all phases.

SCOPE

Govt, 3 Buildings, 3 Phases

COMPLETED

2017-2019

ROLE

Project Manager / Senior PM

CLIENT

Ministry of Justice (via Paragon)

MOJ 102 Petty France - reception
MOJ 102 Petty France - secure environment
MOJ 102 Petty France - fit-out detail
CAT BCOMMERCIALDESIGN & BUILDOCCUPIED BUILDING

British Business Bank

Commercial Office Fit-Out

Cat B fit-out of commercial office space under a fast-track programme. Two-week mobilisation followed by an eight-week build from start to handover. Design and build procurement with close client engagement.

SCOPE

Cat B, 8-Week Build

COMPLETED

2018

ROLE

Project Manager

CLIENT

British Business Bank (via Paragon)

British Business Bank - Cat B fit-out
British Business Bank - office space
British Business Bank - handover
GOVERNMENTSECURECONFIDENTIALCAT BDESIGN & BUILD

Government Client

Confidential

Cat B fit-out for a confidential government client. Scope included strip out, new VRF system, ceilings, partitions, reception, structural works and a new staircase. High-security specification maintained throughout.

SCOPE

Cat B, High-Security

COMPLETED

2019-2020

ROLE

Senior Project Manager

CLIENT

Confidential Government (via Paragon)

Government Client - open-plan office fit-out
Government Client - office interior
Government Client - large floor plate fit-out
GOVERNMENTHERITAGEDESIGN & BUILDSECUREOCCUPIED BUILDINGCAT B

Government Client

D&B Refurbishment

Design and build refurbishment of a county and family court. Full pre-construction and construction delivery in an occupied judicial building.

SCOPE

D&B Refurbishment, County Court

COMPLETED

2021-2023

ROLE

Senior Project Manager

CLIENT

HMCTS

County Court Chatham - D&B refurbishment
County Court Chatham - live court delivery
COMMERCIALDESIGN & BUILDOCCUPIED BUILDINGCAT B

Old Park Lane Management

Mayfair

High-specification developer headquarters fit-out in a prime Mayfair location. Strong focus on quality of finish, design detail and programme control delivered under design and build procurement.

SCOPE

High-Spec HQ, D&B

COMPLETED

2023-2024

ROLE

Senior Project Manager

CLIENT

OPLM (via BW: Workplace Experts)

Old Park Lane Management - high-spec fit-out
Old Park Lane Management - HQ interior
Old Park Lane Management - design detail
Old Park Lane Management - Mayfair headquarters

Further projects

Additional delivery record.

Projects completed as PM or Senior PM not covered in the featured cards above.

ProjectLocationTypeRoleYear
Russell Square HouseHolborn WC1Cat A & Cat B, Live, ReceptionPM2015-2016
Home Office, Lunar HouseCroydon CR9Cat B, ReceptionPM2016-2017
Ministry of Justice (Secure Building)LondonCat B SecureSenior PM2019
Govt Courts Programme, KentKent4 Courts, Full Pre-ConSenior PM2020-2021
Government Client, CanterburyCanterburyCat B D&BSenior PM2021
125 Old Broad StreetCity EC2Live, Reception, PhasedSenior PM2023-2024
16 Palace StreetWestminster SW1Reception, Cat B D&BSenior PM2024

FULL PROJECT REGISTER AND CV AVAILABLE ON REQUEST.